04 NCAC 19P .0502           METHOD OF ADMINISTRATION

(a)  Recipients may delegate to nonprofit subrecipients the responsibility of undertaking or carrying out ESGP activities pursuant to 24 CFR 575.3 and 24 CFR 575.23.  This does not prohibit the designation of an administering agency, so long as no ESGP funds are used for administrative costs.

(b)  NRCD shall make payments of ESGP funds to recipients on a cost‑reimbursement or cost‑incurred basis.  Recipients shall request payment of ESGP funds in a manner prescribed by NRCD.

(c)  All payments of ESGP funds to recipients must be for costs incurred during the period of the grant.  Recipients will not receive payment for costs incurred before the execution of the Grant Agreement.

(d)  All grant funds must be expended or costs incurred within 180 days of the date of the grant award.

 

History Note:        Filed as a Temporary Rule Eff. April 4, 1988 for a period of 180 days to expire on

October 1, 1988;

Authority G.S. 143‑323; 143B‑10; 24 C.F.R. 575;

Eff. October 1, 1988.